⚙️ Takt Settings
Purpose
Takt Settings is the setup interface users interact with after checkout or when beginning a free trial. It’s designed to streamline the configuration of areas, zones, tasks, and overall project structure in a simple, intuitive UI.

🔁 Phases
- First phase is created by default for setup
- Rename, reorder, or add new phases
- Save setup to auto-generate schedule view with changes
🧱 Area & Zone Configuration
- Adding Areas: Simply type an area name and press Enter. Areas could represent floors, buildings, or distinct work sections in your construction site.
- Creating Zones: After an area is created, add zones (e.g., Zone 1, Zone 2) within that area. Zones define smaller work segments and form the basis of flow units across the takt plan.
- Modifying Structure:
- Duplicate areas to save time when layouts are similar.
- Drag and drop areas or zones to reorder them visually in the interface.
- Delete areas or zones with the trash icon if they are no longer needed.
This step creates the spatial backbone of your takt plan, allowing you to visualize how work will progress

✅ Task Configuration
- Type and press Enter to add each task
- Tasks are assigned colors randomly (editable)
- Choose colors from defaults, other projects, or create custom ones
- Copy tasks from another phase or project
- Option to begin with a blank canvas to add one-off tasks directly in the schedule view. For more information about how the blank canvas work, see here.

🧾 Task Properties Modal
Basic Fields
- Name, Code, Description: Editable fields shown in schedule views and reports
Company Tags
- Type the name of a vendor or subcontractor to create a tag
- Once created, company tags are reusable across tasks within the same project
- Used for assigning ownership and filtering schedules
For additional information about company tags and their functionality, see here.
Task Period
- Default: 5 days
- Can be adjusted individually per task
Flow Options
- As Soon As Possible: Scheduled immediately per dependency logic
- As Late As Possible: Scheduled latest per dependencies
- Continuous: Used for uninterrupted crew flows (e.g., traveling teams). For additional information about the continuous flow, see here.
Reverse Task Sequence
- Toggle on/off to generate schedule starting from last zone and flowing upward
For additional information about the Reverse Task Sequence, see here.
Crew Details
- Crew Size: Number of people per crew
- Number of Crews: Parallel crews on the same task
Crew sizes can also be managed at the subtask level. For additional information on how to do this, see here.
Crews can be viewed in the workforce histogram in the schedule view. For more information, see here.
Quantities & Units
- Define unit (e.g., kilos, meters)
- Enter quantity and total cost
- Cost is distributed across days and shown in histogram
For more information about how quantities and costs are displayed in the histogram, see here.
Tags
- Create and assign tags to tasks for:
- Filtering views
- Controlling task access
- Tags are searchable and persist across the project
For more information about how the tags work, see here.
Checklists
- Create reusable task checklists
- Reorder items by drag-and-drop
- Enable/disable checklist visibility per task
- Checklists can be edited later and shared across multiple tasks
For more information about how the checklists work, see here.


📅 Dates & Durations Setup
- Choose custom work week (e.g., Mon–Fri or Wed–Fri)
- Set default task period for all tasks in phase
- Define phase start/end date
- Duration is calculated based on zones/tasks
📆 Holiday Setup
- Add single or multi-day holidays with names
- Delete or copy holidays from another phase/project